Cost Optimization Analysis of Energy Efficiency During Compressor Shutdown at Platforming Unit I
DOI:
https://doi.org/10.31004/irje.v4i4.1347Keywords:
Compressor, Recycle Gas, Energy Efficiency, Operating CostsAbstract
The compressor (C-100) located in the Hydrobon & Platforming I unit is designed to meet the need for recycled gas to keep the H2/HC ratio optimal in the Platforming I section and minimise the rate of coke formation in the reactor. In addition, a Compressor (C-100) is used during the start-up process of the Platforming I unit to maximise LPG production. However, PT X is currently focusing on reformatting production to meet market demand, which prompts considering commissioning a Compressor (C-100) for energy efficiency and cost savings. The shutdown of the previous compressor, which consumed 2400 kWh per day at an annual electricity cost of IDR 8,347,273,344.00, has significantly reduced energy consumption. However, other operational costs, such as maintenance and lube oil make-up, remained during the period, with annual expenses of IDR 440,036,956.00 and IDR 48,741,977.00, respectively. In addition, energy from alternative sources such as steam and cooling water also increased to maintain process performance, with total annual operating costs of IDR 56,256,360,451.20 and IDR 179,789,760.00, respectively. Overall, the operating cost of the Compressor (C-100), which includes electricity, make-up lube oil, and maintenance, totalled IDR 8,836,052,276.80 each year. A review of the compressor operation could provide a solution for cost optimisation and energy efficiency for the company.
References
I. Sutton, “Chapter 1 – Risk Manajement,” in Process Risk and Reliability Management Second Edition, Elsevier, 2015, pp. 1-64.
A. Bhusari. Gho, H. Ai, S. Sathananpally, R. A. Mentzer, “Process Safety Incident Across 4 Industries,” Process Safety Prigresss, vol. 39 (2), pp. 1-9, Apr. 2020.
Rialivhuwa Nekhwevha, “Analysis of Key Controbutors to Process Safety Incident in Chemical Process Industry,” Thesis, University of Johannesburg, South Africa, 2019.
Joseph H. Saleh, Rachel A. Haga, Francesca M. Favaro, Efstathios Bakolas, “Texas City refinery accident: Case study in breakdown of defense-in-depth and violation of the safety–diagnosability principle in design,” Elsevier, Engineering Failure Analysis, 2014, pp 121–133.
Noor Diana Abdul Majid, Azmi Mohd Shariff, Risza Rusli, “Process Safety Management (PSM) for Managing Contractors in Process Plant,” Journal of Loss Prevention in the Process Industries, Jun. 2015.
Penn State Environmental Health and Safety, "Compliance Guidelines for Pre-Startup Safety Review," PSM-SY-UN-016, Sep. 24, 2014.
M. Young, The Technical Writer’s Handbook. Mill Valley, CA: University Science, 1989.
Energy & Power Practice, “Pre-Startup Safety Review: Risk Engineering Position Paper – 06,” March, 2016.
Wawan Gunawan, “Studi Efisiensi Boiler Terhadap Nilai Kalor Batubara Pada Boiler Jenis Pulverizer Coal Kapasitas 300 T/H,” Jurnal Intent: Jurnal Industri Dan Teknologi Terpadu, 3(2), 122-130, 2020.
Suci Ramadhani “Analisis Potensi Bahaya Pada Bagian Boiler Pembangkit Listik Tenaga Uap (PLTU) Menggunakan HIRARC di PT. Indonesia Power Kabupaten Barru,” Skripsi, Universitas Islam Negeri Alauddin Makassar, 2022.
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2024 Lian Safitri, Budi Sulistiyo Nugroho, Zahru Wilda Pratiwi, Abdul Jalil, Wanda Trihadi, Zulkarnain

This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.